§ 136-34. Industrial discharge permit transfer.
Latest version.
-
A.Industrial discharge permits may be transferred to a new owner or operator only if the permittee provides at least 30 days' advance notice to the Director of Public Works, and the Director of Public Works approves the industrial discharge permit transfer. The notice to the Director of Public Works must include a written certification by the new owner or operator which:(1)States that the new owner and/or operator has no immediate intent to change the facility's operations and processes that generate wastewater to be discharged to the Lebanon Treatment Works;(2)Identifies the specific date on which the transfer is to occur; and(3)Acknowledges full responsibility for complying with the existing industrial discharge permit.B.Failure to provide advance notice of a transfer renders the industrial discharge permit void as of the date of facility transfer.